Construction Permits in Georgia: Requirements, Procedure and Practical Considerations
Permit or notification
Construction is governed by the Code on Spatial Planning, Architectural and Construction Activities and Government Resolution No. 255, amended repeatedly, for example by Resolutions No. 573 and No. 631 of 2021.
The requirement turns on the building's class, set out in the Resolution's annex, not on size or height alone: a class attaches to the whole building, and where several parameters apply, the highest class prevails.
Lower-class works may fall under a simplified or notice regime, while repairs, under the Resolution, require no permit.
What to check before you build
Start with ownership and cadastral data in the Public Registry (extract fees).
Then establish zoning, development parameters and special regimes: the Environmental Assessment Code (amended, for example, in 2023) and the Law on Cultural Heritage may require further decisions or consents, and the heritage portal is a starting point.
The Code also allows permit issuance to be suspended for up to 12 months while an urban plan is drafted. Tbilisi's rules do not automatically apply in other municipalities.
Procedure and timing
A permit is issued in stages: land-use conditions, project agreement, permit. Topographic and engineering-geological surveys are mandatory for Classes II-IV; there is no universal document list, since it depends on class, location and the works.
According to a Zugdidi municipal guide, review takes 10 or 20 working days at the first stage, 17 at the second and 5 at the third; design work and curing deficiencies sit outside those periods.
Permits are administrative acts subject to challenge under the General Administrative Code, so watch statutory time limits.
After the permit and main risks
Build strictly to the approved project and permit conditions; any deviations require formal approval.
The consequences of building without a permit depend on the violation, including stoppage of work, heavy administrative fines, or mandatory demolition.
Allocate responsibility, warranties, and deadlines clearly in contracts with contractors under the Civil Code.
Key Takeaway
Conducting a rigorous legal check before construction begins is far less costly than curing violations afterwards. See our civil law, business law and court representation services, or book a consultation.
Frequently Asked Questions: Construction Permits in Georgia: Requirements, Procedure and Practical Considerations
When is a construction permit required?
Who issues the construction permit?
How long does it take to obtain a permit?
What happens if you build without a permit?
Is commissioning the same as a building permit?